In the construction industry, proper planning is the backbone of every successful project. One of the most important tools for clarity and cost control is the Bill of Quantities (BoQ). For contractors and clients alike, the BoQ is a roadmap that lists the work, materials and labour a project needs, item by item. Because every bidder prices the same detailed breakdown, everyone understands the scope of work and tenders can be compared fairly.
This guide explains what a BoQ is, how it is measured and priced, and the different types: firm, approximate and notional bills. It also covers how a BoQ supports the tender process, cost control and the valuation of work on site, and how it relates to the drawings and specification.
What is a Bill of Quantities (BoQ)?
A Bill of Quantities is a document that lists, in measured quantities, all the work needed to complete a project. It is usually prepared by a quantity surveyor or estimator from the drawings and specification. Each item has a description, a quantity and a unit (m, m², m³, tonnes or number), and contractors add a rate to each item to arrive at their price.
In the UK, bills for building work are measured to the RICS New Rules of Measurement, NRM2, which replaced the older SMM7 in 2013. A common standard means every contractor reads the items in the same way, which reduces misunderstandings and makes the BoQ a reliable basis for estimating the total cost of construction, tracking expenditure and managing cash flow.
A typical BoQ is divided into preliminaries (site set-up, management, scaffolding and welfare), measured work sections organised by element or trade, provisional sums for work that cannot yet be measured, and a summary. Together these give a structured picture of the whole project for budgeting, resource planning and cost control.
What a BoQ Looks Like
Each line of a priced bill multiplies the quantity by the contractor's rate. The extract below uses typical late-2026 UK rates, supplied and fixed, excluding VAT:
| Item | Description | Qty | Unit | Rate | Amount |
|---|---|---|---|---|---|
| A | Cavity wall: facing brick outer leaf, 100 mm block inner leaf, cavity insulation | 60 | m² | £240 | £14,400 |
| B | Facing brickwork, half-brick skin, stretcher bond | 45 | m² | £160 | £7,200 |
| C | 12.5 mm plasterboard on dabs with skim finish to walls | 180 | m² | £35 | £6,300 |
Real rates vary with specification, quantity and location: London is typically 20-30% higher, South East 5-15% higher, and the North, Wales and Scotland about 5-15% lower for labour-heavy work.
Types of Bills of Quantities
There are several types of Bills of Quantities, each suited to a different stage of design and a different way of procuring the work. The most common are the firm BoQ and the approximate BoQ.
Firm Bill of Quantities
A firm BoQ is prepared once the design is complete and all the information is available. It is the most detailed type, with exact quantities for all the work. That makes it the right basis for a lump-sum contract and gives an accurate view of the total cost of the project.
A firm BoQ reduces risk and the chance of disputes, and gives a sound basis for cost control. Contractors and clients both benefit from the certainty it provides, because it sets out everything needed to complete the project and gives clear expectations.
Approximate Bill of Quantities
An approximate BoQ is used when the design is not yet complete and exact quantities cannot be measured. It allows the project to go to tender earlier: contractors price approximate quantities, and the actual work is remeasured and valued at the tendered rates as it is built.
Its flexibility allows for changes as the design develops, but the final cost is less certain until the work is remeasured. Where time allows, the approximate bill can be replaced by a firm bill once the design is finished.
Notional Bill of Quantities
A notional BoQ is used when the design is too uncertain even for approximate quantities. It describes the type of work expected, often based on a similar past project, and contractors price it to establish a schedule of rates. The actual work is then measured and paid at those rates. Notional bills suit fast-track projects and term contracts, but leave the client with the least cost certainty at the start.
The Role of BoQ in the Bidding Process
One of the most important roles of a BoQ is in the tender process. Every contractor prices the same quantities and specification, so the client can compare bids on an equal footing. This standardisation reduces confusion and keeps the tendering process transparent.
During tendering, the BoQ gives contractors a structured way to price their work, item by item, covering labour, materials, plant and their overheads and profit. Clients can then evaluate bids accurately and choose a contractor who offers value while meeting the project's requirements and terms and conditions.
A key benefit of a BoQ at tender stage is that it reduces pricing discrepancies. Without one, each contractor measures the drawings and specification separately and may interpret them differently, which leads to large variations in price. A properly prepared BoQ removes most of that risk, because all bids are based on the same quantities.
Benefits of Using a BoQ in Construction Projects
A BoQ offers many advantages in construction project management, especially for cost control, resource planning and communication between client and contractor. It gives a detailed, structured overview of what is needed to complete the project.
A well-prepared BoQ makes cost estimating more accurate, because every part of the project is accounted for, from materials and labour to preliminaries and contingencies. This detailed breakdown helps keep the budget under control, avoid overspending and manage cash flow.
The BoQ is also used throughout construction. Interim valuations compare the work completed on site with the items in the bill, so the contractor is paid for what has been built. Variations are valued using the bill rates, which makes changes quicker to agree and keeps the final account under control.
Finally, a BoQ reduces the risk of disputes. Because it defines the scope clearly and gives a transparent basis for pricing, there is less room for misunderstanding about what was included in the contract price.
Preparing a full BoQ takes time. A quantity surveyor's full service on a residential new build typically costs 1.5-2.5% of construction cost, and a cost plan alone about 0.5-1.2%. On smaller projects, an independent estimate such as one from estiMedes measures and prices the drawings item by item in a similar format.
Conclusion
The Bill of Quantities is an indispensable tool in construction, giving a detailed and structured basis for planning, budgeting and delivering a project. Whether it is a firm BoQ with exact quantities, an approximate BoQ used to tender early or a notional bill that sets a schedule of rates, it brings transparency, fairness and efficiency to the process.
By setting out every resource needed to complete a project, the BoQ helps contractors and clients control costs, avoid disputes and value work fairly. For any construction professional, understanding how to read, price and use a BoQ is essential to delivering projects on time, within budget and to the satisfaction of everyone involved.